CONSTRUCTION REPORT

Construction Gallery - January 05, 2017

LQF – View looking west – Train 1, Area 1105 Lube Oil Cooler Structure
 
 
PTF - Unit 62 View looking N/W – 62E-40 Gas/Gas Cold Box Exchanger & 62V-40 Absorber
 
LQF – View looking south – Train 2, Area 1291 Pipe Rack
 
 
LQF - View looking northwest – Unit 17, Area 1702 Central Control Building Foundation
 
PTF - Unit 61 View looking southeast – 61V-20 Amine Contactor
 
 
PTF – View looking northwest – 61-EB-01 Substation
 
 
PTF – Unit 65 Aerial View – 65-OB-01 Admin-Maintenance-Warehouse Building
 
>
 
 
LQF – View looking east – Train 1, Area 1103 MCHE Scaffolding
 

THE ISLE - FREEPORT LNG REPORT FROM QUINTANA ISLAND

THE ISLE - GALLERY