CONSTRUCTION REPORT

Construction Gallery - October 25, 2018

LQF – Train 1 Control Panel testing
LQF – View looking north - Unit 13, 1391 Pipe Rack
LQF – View looking north - Unit 18, Area 15001 18IB-05 Analyzer Enclosure
LQF –  View looking southwest - Unit 13, Area 1302 Vaporizers
PTF – Unit_70_Piping_Tie-Ins
PTF – West side Unit 61
PTF - West side Unit 62
PTF – West side Unit 63
SRMS - 42-inch Pipe Installation

Q03 - 2018 >

THE ISLE - FREEPORT LNG REPORT FROM QUINTANA ISLAND

 

THE ISLE - GALLERY